Highlights
- The original claim of damages for Grace Baptist ministries was submitted to FEMA at a value of over $70 million. This was the estimated cost to rebuild the campus as it was, but up to present codes.
- The new master plan was originally estimated to cost $65 million. The approved master plan is a complete redesign of our campus bringing all ministries to our original capacity, yet with significant improvements in efficiency, effectiveness, and security.
This is not a rebuild-it is a new build, a long range vision for the future.

- Total spent on the construction project by the end of December 2022 was about $23 million. This included paying for debris removal, demolition, purchase of adjacent 4+ acres, remodel of the Children’s Center and mission house, grading 20+ acres, installing below-ground infrastructure, and initiating new construction.
- The cost to finish the entire master plan is yet to be determined due to the need for re-bidding all remaining construction. With soaring inflation and building supply chain issues, some have suggested an estimate of $45 million to $55 million may still be needed for completion of the entire master plan.

- The pending Letters of Obligation from FEMA are expected to be finalized once costing re-estimation is completed, enabling us to initiate the process for restarting work onsite. The first objective will be to complete that which is already under construction, with the goal of occupancy in about 8 - 10 months after work begins. Work will continue through the final phase with adequate funding.
- Pursuit of additional funding to fill the remaining gap continues for completion of the master plan. Individuals are encouraged to consider what God may have them contribute. Charitable foundations are also being approached for support.

